Kospel EPJ Optimus: GB
GB: Kospel EPJ Optimus

Safety instructions
1. Read and strictly follow the installation and operating instructions to ensure a
long life and reliable unit operation.
GB
2. The unit must be in good technical conditions and must be correctly assembled
before use.
3. The unit should always be vented before initial start-up. Vent the unit each time
after the water has been emptied from the heater or pipes (e.g. when water supply
system has been repaired or maintained).
4. The unit should be connected to electrical system and the reliability of re protec-
tion system should be tested by a qualied person.
5. The unit has to be earthed or neutrally grounded.
6. EPJ-4,4 and EPJ-5,5 must be connected to the mains through a cable box.
7. The unit must not be installed in the place which is exposed to the danger of
0
explosion and place in which the temperature may go down below 0
C.
8. The unit must be connected to the cold water supplies only.
9. Do not use when the water has been emptied from the unit or pipes (e.g. when
water supply system has been repaired or maintained).
10. Cut off power supply to the unit before you take off the product enclosure.
11. This unit can work with the tap set included in the product box only.
11. The tap set works as an air vent and therefore, cannot be connected to any valve
or a connector that is not recommended by the manufacturer.
12. Failure to install the lter on water supply pipe can cause unit damage.
13. Appropriate precaution must be taken when using hot water. Temperature of
0
water over 40
C may cause hot feeling and can be dangerous for children.
15. If the inseparable supply cord will become damage, it should be replaced at the
manufacturer or in special repair shop or by a qualied person in order to avoid
all risks.
This appliance is not intended for use by persons (including children) with reduced physical, sensory or
mental capabilities or lack of experience and knowledge, unless they have been given supervision or
instruction concerning use of the appliance by a person responsible for their safety.
Children should be supervised to ensure that they do not play with the appliance.
EPJ_f.372
11

Installation – Assembly
1. Fix the mixer tap set on water supply
pipe.
2. Connect the heater to the tap body
with nuts, gaskets and the lter.
3. Allow water mains pressure get to
the tap.
4. Open the tap and check for leaks.
Do it without the spray- head on.
Some impurities which come from
the installation may appear.
5. Vent the water installation.
6. Put the spray-head on.
7. Plug the heater:
• EPJ-3,5 plug to an earthed socket,
• EPJ-4,4 and EPJ-5,5 connect to mains
through a cable box.
Electric installation should be equipped with residual current protective de vices
and other solutions which will ensure disconnecting the heater from the source
of power (intervals between all their poles should not be less than 3mm). This
relates to EPJ-4,4 and EPJ-5,5.
Venting
1. Shut off electric supplies to the heater
2. Turn the ow on (turn the hot water tap on) in order to vent the water installation
(for about 15-30 seconds), until the ow of water becomes constant and even.
3. Shut off the ow.
4. Switch on the electric supplies.
The venting process must be repeated each time after the water has been
emptied from the unit or pipes.
12